• SVCS Capital Project
    7/26/17 Updated

    General Information: The Capital Project was voted on in March of 2015. At that time the community approved the project with the building and grounds upgrades listed below. The project was sent to NYS for approval. The project was approved by NYS in the fall of 2016.

    The following chart is a list by building or area that will be completed in this project.

    Building or Area

    Approximate Time Frame

    Main Building

    Roof

    Delivery: June 21
    Begin: June 26
    Complete: August 21

    Replace Fire Alarm Wire

    Begin: May 15
    Complete: Approximately August 19

    HS Principal Office:
    Complete Renovation

    Begin: June 26
    Complete: Approximately August 28

    Family Consumer Science Room:
    Complete Renovation

    Begin: June 26
    Complete: Approximately August 28

    White Boards Replaced

    Begin: August 21
    Complete: Approximately August 28

    Ag. Lab, Ag Storage Building, Greenhouse

    Ag. Lab:
    Complete Renovation-

    1. Add Bathroom
    2. Separate and upgrade kitchen
    3. New FRP for walls
    4. Roof
    5. Siding

    Begin: May 15
    Complete: Approximately August 28

     

    Ag Storage Building:

    1. New boiler
    2. Enclose work space
    3. Add roof bridge for piping

    Begin: May 15
    Complete: Approximately August 11

     

    Greenhouse:

    1. New Heat fins

    Begin: May 15
    Complete: Approximately August 11

     

    Bus Garage

    1. Coat Roof
    2. Wiring Duct work

    Begin: 4- 2017
    Complete: 8-2017

    Site Work

    Trenching behind Bus Garage

    Complete

    Athletic Fields:

    1. ADA Accessible

    Begin: August 10
    Complete: Approximately August 30

    Tennis Courts:

    1. Resurfaced one
    2. Remake one into Basketball Court

    Begin: prepared
    Complete: Approximately August 25

    Main Parking Lot: (The Main Parking Lot will be closed for the entire summer.)

    1. Complete renovation
    2. Reconfiguration

    Begin: June 26
    Complete: Approximately August 25

    Access Road:

    1. Complete Resurfacing

    Begin: August 14
    Complete: August 31

    Playground

    Begin: August 7
    Complete: 31